     Review Questions



     1.  Which of the following is not a key component of scope planning?

         A.  Work breakdown structure (WBS)

         B.  Scope statement

         C.  Project charter

         D.  Scope management plan

     2.  The scope statement provides which of the following?

         A.  A basis for a common understanding of the project and for making future

              decisions regarding the project
         B.  A detailed list of all resources required for project completion


         C.  A schedule of all the key project activities

         D.  A process for managing change control

     3.  Which of the following is a characteristic of a WBS?

         A.  A cost center structure for the project that describes the work of the project and
              the costs per work component to complete the deliverables

         B.  A deliverables-oriented chart of the work of the project with assignments
              showing the project teams responsible for the work components

         C.  A deliverables-oriented structure that describes the detailed tasks required to

              complete the deliverables

         D.  A deliverables-oriented structure that defines the work of the project