programmer that any future changes must be approved by you.
B. Request that the programmer remove the coding for the new features, because
he is outside the boundaries of the original scope statement.
C. Contact the appropriate functional manager, and request a replacement for this
programmer.
D. Determine the source of the request for the new features, and put this change
through the change control process to determine the impact of the changes and
obtain formal approval to change the scope.
2. Which of the following is not a type of change?
A. Corrective actions
B. Defect repairs
C. Performance corrections
D. Preventive actions
3. This entity is responsible for reviewing change requests, reviewing the analysis of
the impact of the change, and determining whether the change is approved, denied,
or deferred.
A. CAB
B. CCB
C. CRB
D. TRB
4. Which of the following should be established as part of the change control system
in the event the change control board (CCB) cannot meet in a timely manner?
A. Emergency change request procedures
B. Procedures for analyzing the impacts of change and preestablished criteria for
determining which changes can be implemented
C. Process for documenting the change in the change request log
D. Coordination and communication with stakeholders
5. After a change request is submitted, all of the following steps occur prior to being
reviewed by the change control board except for which one?
A. The change request is recorded in the change log.
B. Analysis of the impacts of the change is performed.
C. Specific elements of the project, such as additional equipment needs, resource
hours, quality impacts, and more, are analyzed.