continuous feedback and also uses self-organized and self-directed teams. Which
methodology does this describe?
A. PMI®
B. PRINCE2
C. Agile
D. Waterfall
20. What is a backlog? Choose two.
A. A backlog is the remaining work to be completed in a specific phase of the
project.
B. Backlogs are used in an Agile methodology, and team members choose backlog
items at the sprint planning meeting.
C. A backlog is a list of work that’s prioritized by the product owner, but team
members choose the backlog items to work on.
D. Backlogs are used in an Agile methodology, and team members choose backlog
items at the sprint retrospective.
E. Backlog is work not yet completed but was scheduled for a specific iteration.
283