C.  Fixed price plus incentive


         D.  Cost reimbursable

    15.  You know that the project management plan consists of several project documents
         and, once approved, serves as the baseline for the project. All of the following are
         true regarding the project management plan except which one?

         A.  It’s used during Executing and Monitoring and Controlling phases to determine
              whether the project is on track.

         B.  It’s used during the procurement processes to negotiate with the vendor.

         C.  It is a communication tool.


         D.  It’s used when changes are requested to determine whether the change is in
              keeping with the original goals and objectives of the project.

    16.  This person is responsible for managing the backlog, prioritizing the backlog, and
         updating stakeholders with team progress.

         A.  Product owner

         B.  Scrum master

         C.  Sprint owner

         D.  Project manager

    17.  Team members each describe what they accomplished yesterday, what they will

         work on today, and what obstacles are in their way in this type of meeting. Choose
         two.

         A.  Sprint planning meeting

         B.  Standup meeting

         C.  Scrum meeting

         D.  Project status meeting

         E.  Stakeholder meeting

    18.  These two project management methodologies use an iterative approach. Choose

         two.
         A.  PRINCE2


         B.  Six Sigma

         C.  Waterfall

         D.  Agile

         E.  Critical path

    19.  Your project sponsor has instructed you to use a methodology that allows for



                                                            282