Interest Rate Risk management








                   Example 3





                   (ii)  Gain or loss

                         Initially: sold @ 96.5

                         Close out: buy @ 95%

                         Gain of 1.5%


                         £500,000 × 24 × 3/12 × 0.015 = £45,000

                         Close out

                         Expected interest cost is 100 – 96.5 = 3.5%:

                         £6,000,000 × 0.035 × 6/12 = £105,000

                         If interest rates rise to 5%, the cost will be:


                         £6,000,000 × 0.05 × 6/12 = £150,000

                         This is an increase in cost of £45,000.

                         This is netted off by the gain when the futures position is closed out.


                   Note: a question this detailed is unlikely but it shows the various stages which
                   could all be tested individually.




                  Illustrations and further practice



                  Now try TYU 4 and 5 in Chapter 13