Page 12 - MCOM MODEL ANSWER 2
P. 12

P a g e  | 12

               down the fine in Nakolia amongst others. Given the limited time left, that is, only 75 days to the
               end of this financial year, we can hardly see how this can be achieved.


               RECOMMENDATION

               The Board should prepare itself to issue an Earnings Warning to the markets as we approach
               year end. It is clear that turning the situation around is almost impossible given  that we only
               have  about  75  days  left  to  the  end  of  the  financial  year.  Even  if  we  could  turn  around  the

               challenges  with  the  projected  savings  from  the  SSC  Project,  it  will  hardly  make  a  material
               impact on these numbers.


               ACTIONS

               Investor  Relations  should  work  with  Group  Communications  to  prepare  to  issue  an  Earnings
               Warning to the markets, ideally a few weeks before announcement of results. The Group CFO
               should urgently take the actions proposed below in relation to the SSC Project to squeeze out

               more savings in the last 75 days.

               Shares Center Center (SSC) Project



               This issue is a weakness in our updated SWOT analysis. We identified new transactions to be

               escalated to the SSC in Sadimba to help repeat the same savings of S$6.6 billion we achieved
               in 2014 over 4 years starting this 2016. We expected again to escalate 5.3 million transactions
               over the next 4 years, 25% each year with 1.6 million transactions from Sadimba, 1.9 million

               from  Nakolia  and  1.8  million  from  MCOM  (All  others).  As  of  today,  1.67  million  have  been
               transferred.  Going  by  the  schedule,  1.51  million  should  have  been  transferred  (5.3*  25%  *
               12/10.5). The total cost of processing these transactions across the MCOM group before the

               SSC  Project  was  started  is  estimated  at  S$14,164  million.  New  costs  amounting  to  S$7,685
               million  (BAC)  was  to  be  created  at  the  SSC  in  Sadimba  to  handle  these  transactions  which

               when  netted  of  and  adjusted  for  Payroll  savings  in  Nakolia  (All  Others)  of  S$120  million,
               providing this S$6.6 billion saving. This is the cost that the SCC itself must not exceed if the
               savings was to be realised over the next 4 years. Our key observations include:


               SCHEDULE VARIANCE

               This measures the pace at which we are proceeding to transfer the transactions to the SSC.
               The expectation is that we transfer 25% each year. As of now, MCOM Sadimba is ahead of that
               schedule  by  160%  whilst  Nakolia  is  behind  by  40%  and  MCOM  (All  others)  behind  by  24%

               Overall, we are ahead of Schedule by 31%. It may be that the geographical proximity between
                                                            Developed by The CharterQuest Institute for 'The CFO Case Study Competition 2016'
                                                                          www.charterquest.co.za | Email: thecfo@charterquest.co.za
   7   8   9   10   11   12   13   14   15   16   17