043












                                                                       1  We start building formwork for the walls and columns.  2  The
                                                              1  2  3
                                                                       formwork is properly seal on the slab so the mixture wont  leak out.
                                                              4        3  We start inserting the mixture into the wall formwork by using a
                                                                 5  6
                                                              7        stick.  4  We reused any harden cement by smashing it to little
                                                                       powder then reused it in the mixture.  5  Tape were used to help keep
                                                                       the shape intact.  6  Wire were used in addition to tape.  7  Scale
                                                                       drawing and cut-out for beam formwork.
   39   40   41   42   43   44   45   46   47   48   49