044
1 Drawing of the Top Slab/Rooftop for formwork. 2 Beam formwork is
1 2 3
inserted in the model. 3 Once the concrete beam is cure, We start to
4 5 6 cut-out the rooftop. 4 wire frame and space are added before pouring
the mixture. 5 Extra tape we being used in order to ensure there is no
7 8
9 leakage when mixture is being poured. 6 The mixture is being pour to the
roof formwork. 7 Stones were added to help reduce the consumption of
the cement mixture. 8 The left over mixture is pour all over evenly. 9
The completion of the concrete model.