Page 185 - Safety Memo
P. 185
Safety Memo #14 Procurement of Protective Covers to be readily available ALWAYS
Date: April 4, 2019
To: ACI PROJECT DIVISION
<<MANDATORY>>
Procurement of Protective Covers to be readily available ALWAYS
Per Safety Memo #2, as noted below, Protective Covers are mandated as required on the SAME DAY of rebar(straight/bent)
and all metal or wood stakes installation.
As a proactive measure, each jobsite MUST procure at least 100 protective covers to ALWAYS be readily available, especially
if any impalement hazard exists.
If you have any questions on purchasing the protective covers, please contact Brian Shin for assistance.
Thank you.
Safety is ACI’s number one priority.