Page 36 - Puret Sound Energy Hand Book 1218
P. 36

Chapter 2


               400 A and larger     Remote meter installations that require current transformers shall be mounted on
               panels               permanent support structures that are made of galvanized steel pipe with unistrut
                                    cross-braces, concrete, or masonry blocks. Support structures made of wood
                                    (treated or not) are unacceptable.
                                    The customer shall provide a 3-foot x 3-foot x 3-inch-thick concrete pad surrounding
                                    the meter or holes 2 feet deep that are filled with concrete to anchor the structure.
                                    Meter bases/sockets shall be permanently labeled to indicate the address they
                                    serve. PSE requires engraved phenolic nameplates or adhesive die-cut labels at least
                                    1-inch high. Service will not be established until marking is complete.
                                    NOTE:  Felt-tip pens and label maker tape are not considered permanent marking.
                                    Other requirements specified in this handbook for meter bases/sockets and current
                                    transformer (CT) enclosures apply.
               Remote services      Remote services 800 A or greater require EUSERC outdoor switchgear. Ask your
               greater than         CCS Representative for more information.
               800 A

               Meter post           Remote metering must be:
               and pedestal         •   Accessible for reading and maintenance during normal business hours.
               locations
                                    •   Not be in a walkway or breezeway.
                                    •   Not be in an area that is subject to being fenced or enclosed.
                                    •   Safe parking must be located within 50 feet of the meter.
                                    NOTE: When installed close to PSE’s transformer, all metering equipment must be a
                                    minimum of 3 feet from the transformer and not installed in front of the transformer.