Chapter 3







               Permanent overhead service





               Steps to a successful overhead service installation
                                    The following checklist will assist you in preparing for the installation of an overhead
                                     service (see Figure 15). After you have completed these items, PSE can install the
                                     overhead service line and meter.
                                    •   Check for any local ordinances/covenants that prevent you from obtaining an
                                        overhead service.
                                    •   Call PSE to set up an account and submit an order. Allow adequate time for
                                        possible engineering, right-of-way permits, and easement review.
                                    •   Obtain an electrical work permit.
                                    •   Complete Electric Service Application Single-Family Residential 100E. All forms
                                        can be downloaded at pse.com/customerconstruction.
                                    •   Supply site drawings and load information to your PSE Customer Construction
                                        Services (CCS) Representative.
                                    •   Call CCS to find out where your service line will originate.
                                    •   Determine an acceptable location for your meter base/socket.
                                    •   Provide a path clear of obstructions between PSE’s service pole and your
                                        service mast.
                                    •   Provide the location of any domestic or community water well on your property.
                                    •   Install the required service entrance equipment.
                                    •   Install the service entrance conductors (leave a minimum of 18 inches exposed at
                                        the weatherhead).
                                    •   Verify that the service mast height requirements have been met (see Figure 16).
                                    •   Provide payment for any preconstruction costs determined by CCS.
                                    •   Have the city or state inspect and approve your installation.
                                    •   Call CCS at 1-888-321-7779 to have your service installed and energized.






















               Electric Service Handbook 2017 — Single-Family Residential Projects                          28