Control of Industrial Major Accident Hazards (CIMAH) Report Page 21
Ranhill SAJ Sdn. Bhd. Revision 01
Part B: Information on the Installation Date Aug 2019
B.4.0 NUMBER OF PERSONS LIKELY TO BE ON-SITE
The maximum number of person likely to be present on-site
There are eighteen (18) personnel who are based at the KT1 WTP and twelve (12)
personnel at KT2 WTP which operates on a 24-hours per day basis. The plant
superintendent, technician, office clerical staff and cleaners are working on normal
office hours from 0830 to 1730. The shift cycle consists of two (2) operators on a
three-cycle (8-hour) shift.
• Shift 1: 0700-1500;
• Shift 2: 1500-2300 and
• Shift 3: 2300-0700.
The number of persons likely to be at the KT1 WTP during the day and night time is
shown in Table B.4.0a below.
Number of Personnel Number of Personnel
No. Location
Day Shift Night Shift
1. Administration Building 9 0
2. Treatment Plant 5 2
3. Guard House (Security) 1 1
4. Plant Wide (Cleaner) 2 0
17 3
Total
20
Source: KT1 WTP
Table B.4.0a: Number of Persons On-site at KT1 WTP