4.7.9 Testing and Completion
       Upon completion of the installations, all must be
       fully tested and proved, including airflows. The
       Contractor  must  produce  an  Operating  and
       Maintenance Manual containing:
       •  Details of all equipment supplied,
       •  A  record  drawing  of  the  complete
          mechanical services installation
       •  Copies of all Test Certificates.
       •  Maintenance  Schedules  based  on  the
          manufacturer’s recommendations


       For  projects  in  England  and  Wales,  the  HVAC
       contractor shall also demonstrate compliance
       with Building Regulations Approved Documents
       L2A & L2B. This will include:
       •  Provision  of  details  of  the  efficiency  and
          controls of heating, cooling and ventilation
          systems  in  accordance  with  the  Non-
          Domestic Heating, Cooling and Ventilation
          compliance Guide (2006).
       •  Provision  of  commissioning  certificates
          including air leakage test on the ductwork.

       The  contractor  shall  provide  a  typical  12
       months  spare  filters  for  mechanical  supply  air
       installations.


       It is the contractors responsibility to ensure that
       all  warranties  are  registered  with  the  relevant
       manufacturers  and  suppliers. The  contractor
       must also provide the Franchisee with a record
       of the installation so that an F gas record can
       be  kept  containing  information  on  quantity/
       type of gas on installation, quantity/type of gas
       added during maintenance, dates and results
       of mandatory leak checks etc.








       4.7.9                       Testing and Completion                                3 February 2016