Page 389 - Installation Training Binder FIT1-3
P. 389
B. Check Barrier Layout
1. Layout Barrier per CAD Diagram
2. Verify barrier wall fits around rack, stack or cabinet with 1” of clearance
(Figure 5)
3. Check for Obstructions (Figure 6)
Figure 5 Figure 6
C. Liner Preparation
1. Line up a T-square or other straight tool to one side of a rack stanchion
(Figure 7)
2. Mark line from beginning of rack to end of the straight edge (Figure 8 and
Figure 9)
Figure 7 Figure 8
3. Repeat process for each side of stanchion
4. Ensure liner is firmly taped to ground before moving to next stanchion
Figure 9
EnviroGuard 800-206-9884 Fax 909-624-1772 www.egsintl.com
11/07 rev. A Eagle System Retrofit Installation Setup Instruction - 4 -