Schedule
As identified within the Request for Proposal, Building B will be the first building to be constructed. Bernardon
will provide Schematic Design services for Building A and Building B simultaneously. The total duration of
Schematic Design for Building A and B is reflected in the schedule.
Design Development and Construction Documents will continue for Building B only. Building A will
commence once defined leasing milestones for Building B are achieved.
Project Design Schedule | Pre-Construction
Project to commence within one week of authorization to proceed.
PHASE I Duration (WEEKS) OVERALL PROJECT DESIGN DURATION
Schematic Design (SD) 6 weeks
Initial Concept Development 2 weeks
Concept Revisions 1 week
Final SD Documents 2 weeks
Final Owner Review/Authorization to Proceed 1 week
PHASE II Duration (WEEKS)
Design Development (DD) 8 weeks
Prepare DD Documents 3 weeks
Owner Review Meeting 1 week
Finalize Documents 3 weeks
Final Owner Review/Authorization to Proceed 1 week
PHASE III Duration (WEEKS)
Construction Documents (CDs) 8 weeks
Prepare Construction Documents 3 weeks
Owner Review Meeting 1 week
Finalize Documents 3 weeks
Final Owner Review/Authorization to Proceed 1 week
Issue for Bid/Permitting 4 weeks
CONSTRUCTION COMMENCEMENT