               Schedule


               As identified within the Request for Proposal, Building B will be the first building to be constructed.  Bernardon
               will provide Schematic Design services for Building A and Building B simultaneously. The total duration of
               Schematic Design for Building A and B is reflected in the schedule.


               Design Development and Construction Documents will continue for Building B only.   Building A will
               commence once defined leasing milestones for Building B are achieved.



                Project Design Schedule | Pre-Construction
                Project to commence within one week of authorization to proceed.
                PHASE I                              Duration (WEEKS)         OVERALL PROJECT DESIGN DURATION
                Schematic Design (SD)                    6 weeks
                 Initial Concept Development             2 weeks
                 Concept Revisions                       1 week
                 Final SD Documents                      2 weeks
                 Final Owner Review/Authorization to Proceed  1 week
                PHASE II                             Duration (WEEKS)
                Design Development (DD)                  8 weeks
                 Prepare DD Documents                    3 weeks
                 Owner Review Meeting                    1 week
                 Finalize Documents                      3 weeks
                 Final Owner Review/Authorization to Proceed  1 week
                PHASE III                            Duration (WEEKS)
                Construction Documents (CDs)             8 weeks
                 Prepare Construction Documents          3 weeks
                 Owner Review Meeting                    1 week
                 Finalize Documents                      3 weeks
                 Final Owner Review/Authorization to Proceed  1 week
                 Issue for Bid/Permitting                4 weeks
                                                                                            CONSTRUCTION COMMENCEMENT































               BERNARDON | Proposal for Professional Design Services
               Plantation Square Medical Office Campus, Rehoboth Beach, Delaware | March 22, 2021         Page 7