                    ■ Attendance at a pre-bid meeting;                ■ Perform a punch list review of interior
                    ■ Answer questions and Requests for               core and the exterior of the building from
                    Information (RFIs) from the bidders;              the ground.
                    ■ Prepare addenda if necessary;
                    ■ Review bids and; and                        Should the construction process go beyond eight
                    ■ Assist with the construction contract       (8) months, we reserve the right to invoice on an
                    award.                                        hourly basis and as additional service meetings in
                                                                  excess of those noted above.
               Phase V - Construction Administration
               We understand that you will be engaging a          Additional Services and Exclusions
               Construction Manager (CM) or possibly a General    Our services are limited to the scope of services
               Contractor (GC) for the construction of the project.     described  in this  proposal.   If the  scope of  the
               Our scope of services during construction can vary   project or our services changes, we reserve the
               depending upon the involvement of the Owner and/   right to invoice for Additional Services.  Examples
               or the CM/GC.  We anticipate an eight (8) month    of Additional Services would include:
               construction period for the building core and shell.
               For the purposes of this proposal, we believe our      ■ Making Owner-requested revisions to
               role could include following:                          previously approved drawings;
                                                                      ■ Making “value engineering” changes to
               For the purposes of this proposal, we have assumed     the drawings after receipt of bids;
               a role including the following:                        ■ Providing services after a substantial delay
                                                                      in the project schedule;
                    ■ Answer RFIs during the subcontractor bid        ■ Design and documentation of interior
                    period;                                           improvements in areas other than the
                    ■ Attend one (1) pre-construction meeting;        building core; and
                    ■ Attend monthly, on-site visits (eight (8) in     ■ Selection and documentation of furniture,
                    total);                                           fixtures and equipment (FF&E).
                    ■ Review and sign monthly contractor
                    applications for payment;                     The following are not included in our scope:
                    ■ Review specific shop drawings for
                    architectural, structural, and MEPFP              ■ Civil engineering or any site improvements;
                    building materials and systems as outlined        ■ Landscape   architecture,   including
                    in our book-format specifications;                plantings or hardscape;
                    ■ Coordinate consultants through the              ■ Geotechnical engineering;
                    construction  process.   The  Structural          ■ Construction cost estimating;
                    Engineer will visit the site two (2) times        ■ Voice/data;
                    at the appropriate critical points of
                    construction.  The MEPFP Engineer will            ■ Security; and
                    visit the site up to three (3) times at the       ■ Interior and exterior signage other than
                    appropriate critical points of construction;      that required by code.