Page 11 - Graypvine October 2020
P. 11

“Luckily, we are in an English                        IT infrastructure support, programming, equipment

        speaking country so there                             procurement and installation and commissioning.
                                                              Gray AE Food & Beverage is supporting the Irish
        isn’t much of a language                              design team members to ensure food safety and
        barrier; even though the Irish                        defense as well as our customer’s engineering
                                                              standards are being maintained and honored.
        brogue may be a little tough                            Other challenges with working overseas include

        to decipher at times!”                                dealing with time zones (the project team has
                                                              disregarded the time clock to attend meetings and
                                                              make decisions), different safety procedures and
        testing and commissioning of the facility.            strict ways of managing risk during COVID-19,
          Project ABC is a phased development, and            sourcing and coordinating equipment from the U.S.
        turnover of the concentrates will occur in May and    and EU, and of course driving on the “wrong side
        July of 2021. The team is fitting out 165,550 s.f.    of the road”.
        of the existing 412,571 s.f. warehouse. Since the       Thanks to our amazing team members for their
        building already has walls, ceilings, and cold store   hard work on Project ABC, especially our team
        areas in place, the project is very complex in terms   working in Ireland right now: Chad Jamison,           11
        of coordination and phasing. To help the process,     Project Manager; Joseph Badgett, Site Manager;
        the team has utilized a BIM model, and a complete     Jesse Abel, Safety Manager; Tim Wilson, Project
        interior 3D building scan during construction.        Engineer; Dylan Lewis, Field Engineer and JJ
          Of course, working overseas comes with its          McGuire, MEP Process.
        own challenges.
          “Luckily, we are in an English speaking country so
        there isn’t much of a language barrier; even though
        the Irish brogue may be a little tough to decipher at
        times!” said David.
          “In regards to engineering, the EU is very
        prescriptive in procedures and policies,” said
        David. “Thus providing a design-build solution with
        a phased design and construction approach is very
        challenging. The permitting process is controlled
        by statute, and there is no partial permitting
        allowed. The statute is set at 12 weeks with
        another 4 weeks assumed for RFI clarifications.
        So, when you’re trying to move expeditiously,
        this is a challenge – especially without completed
        engineering or design documents. Luckily, we are
        modifying an existing structure, so there are some
        works that we can begin without full approval.”
          The team has also been tasked with learning
        and navigating a multitude of codes and licensing
        requirements that are different from those in the
        U.S., including COMAH, ATEX, British Standards
        and EU Regulations. In addition to a great
        engineering and design team at Gray Construction,
        the team has partnered with Irish architects and
        designers, and used resources within Gray, Inc.
        Gray Solutions and InLine Engineers are handling
        the process engineering, automation and controls,
   6   7   8   9   10   11   12   13   14   15   16