Page 120 - ASBIRES-2017_Preceedings
P. 120

Nimasha, Dharmawardhane & Appuhamy



       Today, several issues have been identified in     the   construction    delay   and    giving
       this  treatment  process.  One  of  the  major    suggestions       for      case       based
       issues of this industry is construction delay.    organization.Owolabi,    Amusan,     Oloke,
       It is  highly affects both  the  clients  and the   Olusanya, Owolabi, Peter & omuch, (2014)
       consultants.  In  addition,  handing  over  the   have done research on causes and effect of
       project  immediately  helps  to  keep  loyal      delay  on  project  construction  delivery  time
       customers  and  good  will.  Having  efficient    and  investigated  negative  effects  such  as
       water  treatment  and  waste  water  treatment    increased  costs,  loss  of  productivity  and
       companies in Sri Lanka helps to develop the       revenue many lawsuits between owners and
       economy  of  the  country  without  allowing      contractors   and    contract   termination.
       money flow to foreign companies. Therefore        Random  sampling  technique  was  used  in
       the main objective of this study is to idenfity   their study.
       factors that affect the delays in construction
       and to propose the methods that reduce such            A sample of 150 was used in this work.
       delays.                                           A  total  sample  of  ninety-three  (93)  was
                                                         deployed.  A  structured  questionnaire  in
               2 LITERATURE REVIEW                       Likert  scale  was  used  in  data  collection.
                                                         According  to  their  studies  there  are  many
           Delay  is  one  of  the  biggest  problems    factors such as lack of funds to finance the
       often  experienced  on  construction  projects.   project to completion, changes in drawings,
       Delay in construction project has a negative      lack of effective communication among the
       effect   on   clients,   contractors,   and       parties   involved,   lack   of    adequate
       consultants in terms of growth in adversarial     information from consultants, slow decision
       relationships, mistrust, litigation, arbitration    making   and   contractor’s   insolvency,
       and cash-flow problems.                           variations among others introduce delay on
           The duration of a construction project is     construction  projects.  Moreover,  project
       an  important  factor  to  set  forth  when       management      problem,     mistake    and
       entering into a construction agreement. If a      discrepancies    in   contract   document,
       contractor   works    within   a   planned        equipment availability and failure, mistakes
       parameter,  he/she  should  be  able  to  finish   during  construction,  bad  weather,  and
       the construction project in a timely manner.      fluctuation  in  prices  of  building  were  also
       However, compared to other industries, it is      considered as reasons.
       difficult  to  complete  a  construction  project
       in   which    many    construction   trades                  3 METHODOLOGY
       participate and numerous unknown variables            At  first,  it  is  important  to  identify  the
       exist.                                            variables related to this study. As the main
           When      such     difficulties   arise,      objective  of  the  study  is  to  identify  the
       construction  schedules  are  delayed,  and       reasons  for delaying  project, the  dependent
       consequently delay claims occur (Lee, Ryu         variable  was  identified  as  number  of  days
       & Kim, 2005). Rao & Culas (2014) defined          delayed. Based on the visual inspection and
       construction delay as the late completion of      management  experience  about  process  of
       work  compared  to  the  planned  schedule  or    water  treatment  the  following  ten  factors
       contract  schedule.  Construction  delays  can    were  identified  as  independent  variables
       be  minimized  only  when  their  causes  are     which  are  suspectable  to  be  the  cause  for
       identified.  Identified  causes  can  be  defined   projects delays: Delay at mobilization stage,
       as  late  in  revising  and  approving  design    Agreement  preparation  delays,  Payment
       documents, delay in sub contract work and         delays,   Unavoidable    issues,   Planning
       poor  communication  and  coordination            process,  Import  delays,  Local  materials
       change order by owner during construction.        purchasing  delays,  Installation  delays,
       Moreover, they mentioned  how to minimize