Page 18 - Rice & Gardner Training Booklet - Distribute Copy R1
P. 18

03 |Topic 3

                                                  How do you kick off design and construction in support of the bond program?

           NOTES:                                  B. ESTABLISH PROGRAM SCHEDULE

                                                   We use several schedules in our management approach:

                                                   Preliminary Master Project Schedule: This schedule is developed during the
                                                   design phase to detail the tasks for design, procurement, construction,
                                                   occupancy, close-out, and warranty. It includes items like utility tie-ins, other
                                                   activities that interface with the Owner or other contractors, and key
                                                   milestones from the construction portion of these schedules in the proposal
                                                   documents.

                                                   Master Project Schedule: A Master Project Schedule is developed by using
                                                   the construction schedule submitted by the General
                                                   Contractor/Construction Manager-at-Risk. Key tool in managing each project
                                                   to its required interim and final completion dates. Key district dates like
                                                   student testing, furniture delivery and installation and move in will be
                                                   tracked on the schedule. The schedule should be updated based on regular
                                                   meetings with the General Contract/Construction Manager-at-Risk and
                                                   regular team meetings with the district and the design team.

                                                   Short Interval Construction Schedule: The on-site Construction Manager
                                                   meets weekly with the General Contractor/CMAR to review their detailed
                                                   short-term (3-4 weeks) schedules. The schedules must be consistent with
                                                   the requirements of the current Master Project Schedule and the milestones

                                                   in each General Contractor/CMAR contract.

                                                   Completion and Occupancy Schedule: This process begins as information
                                                   becomes available, often while in the design phase. Schedule includes start-
                                                   up and commissioning activities, final inspections, operations training,
                                                   district and TDLR approvals, move-in and operations start-up, Contractor de-

                                                   mobilization, final site restoration, and final acceptance. The project
                                                   managers should develop a responsibility matrix with stakeholders and

                                                   program team early on so everyone understands their role in the project
                                                   from the very beginning.





















          MAY 2017                                                                              RICE & GARDNER | 13
          PROGRAM MANAGEMENT | GUIDE BOOK
   13   14   15   16   17   18   19   20   21   22   23