Page 37 - Rice & Gardner Training Booklet - Distribute Copy R1
P. 37

06|Topic 6

                                          What is the timeline from permitting, advertisement, bidding, board approval and NTP?

            E. RECOMMENDATION TO THE BOARD                                 NOTES:

            In evaluating qualified proposals, the following considerations will be taken
            into account for award recommendations:

              Overall quality and value to the district
              Suitability for the intended purpose and overall cost to the district

            The recommendation, based on an evaluation and ranking of each proposal
            submitted in relation to the selection criteria will be presented to the Board
            of Trustees for award of the contract for construction.












































          MAY 2017                                                                              RICE & GARDNER | 32