14.    SCHEDULE

                          The  Contractor  shall  be  prepared  to  commence  work  immediately  upon receipt  of  a
                   Notice to Proceed.  The currently scheduled contract approval date  is  on or about
                   August 25, 2017.  The Undersigned understands that early completion is important to Cornell
                   University and that schedule will be considered in Cornell University's evaluation of proposals.
                   It is an Owner's requirement that occupancy of the building  be  taken  no  later  than
                   August 1, 2019.  Therefore, time being of the essence, the Undersigned proposes to perform the
                   work in accordance with the following Schedule of calendar days which shall be calculated as
                   beginning on the date of Contract Award:

                          Activity                                   Calendar Days

                          Mobilize                                    20 Work Days

                          Start Work                                  15 Work Days
                          Substantially Complete                      489 Work Days


                          Total calendar days from project
                          Start to Project Completion                 524 Work Days     (7-18-19)

                          The Undersigned encloses herewith an abbreviated form of  CPM  Schedule that
                   demonstrates that the work can be accomplished within the scheduled dates quoted above.