Page 16 - Barr&Barr_Cost Proposal
P. 16
18. UNIT PRICE SCHEDULE
The following Unit Prices are proposed for additions to or deletions from the work. The
Undersigned hereby proposes the Unit Prices be used for this project in accordance with Article
11 of the General Conditions. Upon acceptance by Cornell University, the completed Unit Price
Schedule will become part of the contract arising from this Proposal. The Guaranteed Maximum
Cost will be adjusted for Unit Price work changes that may be incorporated in the Work over the
duration of the Contract as determined by Cornell University and the Architect in accordance
with Article 11 of the General Conditions.
The increase or decrease in the Guaranteed Maximum Cost shall represent the difference
in quantity multiplied by applicable Unit Price, which shall include all charges for labor,
material, waste factor, handling, delivering, storing, restocking, fees, general expenses, taxes,
insurance, labor burdens, engineering, shop drawings, small tools, field and office supervisory
personnel, overhead and profit.
UNIT PRICE ADD DEDUCT
EXCAVATION
A-1 Mass excavation, CY * $ $
40 34
A-2 Structure excavation, CY * $ $
60 51
A-3 Utility trench excavation, CY * $ $
100 85
A-4 Removal of unsuitable soil from $ $
site, CY ** 65 40
A-5 Removal of contaminated soil $ $
from site, CY ** 85 60
A-6 Import controlled fill, CY $ $
105 85
A-7 Compacted backfill, CY $ $
105 85
A-8 Stone sub-base, CY $ $
105 85
ROCK REMOVAL
B-1 Rock ripping, CY $ 0 $ 0
B-2 Rock removal w/hydraulic impact $ 0 $ 0
tool, rubber tire backhoe, CY
B-3 Rock removal w/hydraulic impact $ $
tool, tracked backhoe, CY 0 0
B-4 Break rock - Hard sound rock 60 $ 1,100 $
TSF, CY N/A
B-5 Break rock - Medium hard rock 40 $ $
TSF, CY 900 N/A
B-6 Break rock - Intermediate rock 20 $ 700 $
TSF, CY N/A
B-7 Break rock - Soft rock - weathered $ $ N/A
8 TS, CY 500
* Excludes Trucking and Disposal
** Trucking and Disposal Only
Addendum No. 3 COST PROPOSAL FORM BF-14