15.    SUBSTITUTIONS

                          A.     The Base Bid is predicated on compliance with the Drawings and Specifications
                   without substitutions.

                          B.     The Bidder may offer substitutions for any item noted in the Specifications, with
                   the exception of Form of Contract, General Conditions and General Requirements - Division 1,
                   by listing in the space below the proposed substitution, together with the amount to be deducted
                   from the Base Bid if the substitution is accepted.

                          C.     The Owner reserves the right to accept or reject any proposed substitution.


                          D.     The sum stated includes any modifications of work or additional work that may
                   be required due to  acceptance of substitution.  Substitute materials must be approved and
                   accepted  by  the  Owner  in  writing  before same may be used in lieu of those named in the
                   Specifications.

                   Item and                 Specification
                   Description of           Reference                               Deduction from Base
                   Bid
                   Substitution             Section & Page No.                           Labor         Material


















































                   Addendum No. 3                  COST PROPOSAL FORM                               BF-11