Construction
vehicle access
Staging
Area
20' Construction Create a temporary
gate w/Tracking Pad Egress Path separated
from construction
B B - Improvements to the
Music Studio Bldg.
Music Studio to remain in use during
construction. Maintain access to & from
space during construction
C - Renovation &
Expansion of
No heavy equipment or material the Gymnasium
cross or be placed on Aqueduct
C
Demolition New Underground Detention
work with Header (Below)
8' Construction fence
w/privacy screen (Typ.)
VICTORY HALL
ADDITION/RENOVATION
8' Construction fence w/privacy
screen (Typ.) DOBBS FERRY, NEW YORK
A Emergency
A - New West Entrance
Egrerss
Construction vehicle access
New Work / Notes:
Maintain Pedestrian Access into Addition (Typ.) - CHECK CLEARANCE HEIGHT OF ALL
and around adjacent buildings
EXISTING POWER/TELEDATA LINES
ON CAMPUS PRIOR TO MOBILIZATION
& DELIVERIES.
Material Storage
- MAINTAIN ACCESS TO ADJACENT
Maintain Two (2) Means of Egress out B&B ROADWAYS,DRIVEWAYS &
of Victory Hall during construction SIDEWALKS. 1 07/26/17 CM Bid Package
- ROADWAYS TO BE NO. DATE: ISSUED:
MAINTAINED/CLEANED THROUGHOUT
THE DURATION OF THE PROJECT.
- ALL WORK TO BE COORDINATED SITE LOGISTICS
WITH OWNER PRIOR TO START. PLAN -
Temporary path for pedestrian - PPE SIGNAGE TO BE CLEARLY
access into Victory Hall during West POSTED AROUND SITE Excavation &
Entrance Construction - COLLEGE TO PROVIDE OFFSITE Foundations
20' Construction Fire Hydrant PARKING W/SHUTTLE LEAVING EVERY
gate w/Tracking Pad 15 MINUTES TO CAMPUS
SCALE: NTS