Workmen’s Circle Multicare Center

                                            New Addition and Renovations, Bronx, NY



































          CONSTRUCTION COST        COMPLETION DATE          OWNER
          $38 million              2002                     Workmen’s Circle Multicare
                                                            Center
          SCHEDULE                 CONTRACT TYPE
          27 months                Construction Manager-at-Risk  ARCHITECT
                                                            Pallante Associates







                                                                       PROJECT DETAILS
         Th  is project required the complete renovation of the existing home and       •   Construction occurred in a multi-phased plan
         a two (2) story rooftop vertical expansion and infrastructure upgrade/  that saw the entire building renovated, including
         replacement while the home remained fully occupied.               the boiler plant, kitchen, new electrical services
                                                                           and addition of emergency generators while
                                                                           ongoing day to day functions continued for the
                                                                           residents.
                                                                          •   New residence beds were added with two new
                                                                           fl oors placed on the top of the existing roof.
                                                                          •   Th  e existing masonry façade was discovered to
                                                                           be failing and had to be completely removed and
                                                                           rebuilt during the renovation phase requiring
                                                                           a carefully planned sequencing of spaces to
                                                                           maintain an acceptable bed count.
                                                                          •   All elevators were upgraded and a new freight
                                                                           elevator installed in the core of the building.