NY Hospital Queens

                                          Master Plan - West Wing Addition, Flushing, NY



































          CONSTRUCTION COST        COMPLETION DATE          OWNER
          $119 million             2012                     NY Hospital Queens
          SCHEDULE                 CONTRACT TYPE            ARCHITECT
          29 months                Construction Manager-at-Risk  Perkins Eastman








                                                                       PROJECT DETAILS
         The New York Hospital Queens Master Plan Project featured a       •   A new 372 car garage was constructed on an
         seven-story, 202,000 square foot addition, as well as renovations to   adjoining site to replace the facility that was
         adjoining areas of the Hospital. Th  e West Wing Addition includes a   removed to make way for the new West Wing
         new Ambulatory Surgery Center, new main entrance and lobby, Non-  Addition.
         Invasive Cardiology Suite, two fl oors of Med/Surg beds and Medical
                                                                          •    Two shell fl oors were designed for an
         Practices offi  ces on the basement level.
                                                                           additional 80 Med/Surg beds in the future.

                                                                          •   Multiple phases allowed the continued use of
                                                                           key areas of the hospital during construction.

                                                                          •   Rigorous infectious control program was
                                                                           established to ensure high standards were met by
                                                                           all.