Page 66 - TECHNICAL SPECIFICATION FOR PALM OIL REFINING_rev.1 - Copy_Float
P. 66
OFFER NO. KMIPL/P16E0097R7
100 TPD PHYSICAL REFINERY AND FRACTIONATION
Page No. 66/69
Battery Limits of Refinery
1. Feed oil to be provided at inlet of Feed pumps
2. Soft water to be provided at inlet of water header
3. Phosphoric acid to be provided at inlet of phosphoric acid tank.
4. Bleaching earth to be provided at inlet of earth hopper
5. Fuel oil for thermic fluid Heater to be provided at inlet of heater burner
6. Process water to be provided at inlet of water tank
7. Electric power 3 phase 380 volts to be provide at incomer of sectional
control panel
8. Instrument air to be provided at inlet of air header.
9. Any other equipment and services not expressly mentioned in our offer
are also excluded from our scope of supply (except required within battery
limits for guaranteed performance of plant).