Page 66 - TECHNICAL SPECIFICATION FOR PALM OIL REFINING_rev.1 - Copy_Float
P. 66

OFFER NO. KMIPL/P16E0097R7
                                                      100 TPD PHYSICAL REFINERY AND FRACTIONATION
                                                                                              Page No. 66/69


                                              Battery Limits of Refinery

                   1.  Feed oil to be provided at inlet of Feed pumps

                   2.  Soft water to be provided at inlet of water header


                   3.  Phosphoric acid to be provided at inlet of phosphoric acid tank.

                   4.  Bleaching earth to be provided at inlet of earth hopper

                   5.  Fuel oil for thermic fluid Heater to be provided at inlet of heater burner

                  6.  Process water to be provided at inlet of water tank

                  7.  Electric  power 3 phase 380  volts to be provide at incomer of  sectional

                       control panel

                  8.  Instrument air to be provided at inlet of air header.


                  9.  Any other equipment and services not expressly mentioned in our offer

                       are also excluded from our scope of supply (except required within battery

                       limits for guaranteed performance of plant).