                          Specification of Engineering Services

                        Kumar Metal Industries Proposal includes only the items specified
                        together with the following engineering services supplied upon execution

                        of the contract and applicable only to the items supplied:


                    1.   Kumar will provide plant and equipment drawings showing positional

                        relationship of the items to be supplied. (And indication of any necessary

                        access walkways and platforms if applicable).


                    2.   The above mentioned arrangement drawings will provide indications of

                        static and dynamic loads and the type of equipment “anchoring”
                        methods used.  These drawings will provide sufficient information to

                        allow for the Purchaser to design the building and foundations.


                    3.   Flow diagrams for process and utilities showing the main process flow,

                        pipeline sizes, valves and fittings and  instrumentation. Indications of
                        where insulation is necessary will be marked on these drawings.



                    4.   Specifications for piping, showing material of construction for pipes,
                        valves and fittings and miscellaneous items for the various services.


                    5.   Specifications in terms of material and thickness for insulation.



                    6.   Drawings showing the outline dimensions, connection orientations and
                        weights.



                    7.   Electrical drawing showing the control of the plant with process.