Remove the Pump Station from the packaging crate and position it into its final location and lag it to the floor. This
applies for any of the three pumping stations. The types of utilities that are necessary depend on the pumping
station that was purchased so follow the next steps that apply to your site.
10HP Pumping Station
See Nozzle Chart on the next page.
25HP Pump
1. The hose that will run from the pumping station to the Lexair™ manifold will be a field supplied line. The
specifications of this line require a minimum rating of 1500 PSI and a minimum bend radius of 8’’. This line
should be kept as short as possible to limit losses that occur in long hose runs.
2. Run the field supplied 3/4” hydraulic line with the above specifications from the outlet of the pumping station
up along the entrance side of the boom, attach the line using the 6 supplied Stauff™ clamps, then run thru
the smallest window on the utility hose support and finally tightened onto the Lexair™ manifold. See running
hoses and utilities in the installation of the boom for further instructions. Be sure to secure the hose in all