Page 12 - SideWinder®
P. 12
®
SideWinder
Inspection
Equipment to Inspect Before Installation
Uncrate the driver and passenger side SideWinder® assemblies and inspect for damage.
Note: If there is any damaged equipment, file a claim with the trucking company immediately.
Receiving party is responsible for filing claim with trucking company. Notify your local
distributor or Belanger, Inc. immediately if shipment is determined damaged or incomplete.
Before removing the SideWinder® assemblies from the shipping pallets there are several electrical and
component connections on the units that should be inspected. Inspect the following:
Motor Cables
The SideWinders® each have a 1HP 3-Phase motor that comes wired for the voltage selected
when ordered which was either 208/230, 460 or 575 VAC.
1) Refer to the yellow sticker on the SideWinder® Assemblies Electrical Junction Box to verify
that the motors are wired correctly for the site voltage.
CAUTION: CAUTION: CAUTION:
FACTORY WIRED FACTORY WIRED FACTORY WIRED
208/230 VAC 460 VAC 575 VAC
2) Verify the electrical cables for the motors are high enough so they will not drag on the floor
when installed. If necessary, zip tie the motor cable to the Gearbox Mount Plate and for
additional protection spiral wrap the cable to prevent wear.
Junction Box
Gearbox Mount Tie Bar
Plate Sleeve
Motor Cable Motor Cable
Motor/Gearbox
10 Belanger, Inc. * PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681 1MANUL955