Page 16 - SideWinder®
P. 16
®
SideWinder
Installation
Tunnel Placement Overview
When placing the SideWinder® assemblies, tunnel depth will vary from site to site. Be sure to allow an
adequate operating envelope.
There are two traditional installation configurations for the SideWinder® assemblies.
Standard, stand alone
®
Staggered with a set of Quick Fire Plus assemblies
Note: The dimensions shown below can vary depending on surrounding equipment locations. It is most
important that the SideWinder® is moved through its full range of motion to ensure conveyor clearance
before lagging to the floor.
Standard, Stand Alone Configuration
Equipment around the SideWinder® should give ample room for the wheels to pivot within the
working envelope.
204”
Operating Envelope
58”
DIRECTION
of
TRAVEL
64”
174”
174" dimension is taken from the outer edge of each base plate.
64" dimension is taken from the outer edge of the driver side base plate to the inside edge of the conveyor guide rail
Heavy dotted lines show the proper operating envelope
Note: The above image is shown with cleaning material installed to indicate the operating envelope
required for proper function.
14 Belanger, Inc. * PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681 1MANUL955