Page 25 - Airblade® Dryer - Mix and Match
P. 25

AIRBLADE® DRYER Mix and Match



                       Installation


                       2-Nozzle Frame Assembly: Floor Mounted

                              1)  Locate the following parts:

                                                 Item              Qty    Corner Clamp Pieces (2)
                                     Dryer Leg Weldment             2

                                     Corner Clamp Assembly          2

                                     Black Plastic Caps             4
                                     Lag Bolt 3 Zinc 5/8 x 6        8













                              2)  Locate the skid that the head beam assembly  shipped on. Clamp the head beam
                                 assembly to the forks of the forklift and position it in its tunnel location.

                              3)  Lift it until there is a 91” clearance from the bottom surface of the head beam to the floor.


                              4)  Slide one of the clamp assemblies and one of the legs into place as shown below but do
                                 not tighten the bolts until the height is set and the frame has been leveled. Be sure
                                 the base of the legs face the entrance of the tunnel.

















                                                             Before                                  After

                              5)  Secure the clamp and leg into place on the other side. Do not tighten the bolts until
                                 the height is set and the frame has been leveled.










                        1MANUL011                             Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (810) 349-7010 * Fax (810) 380-9681                            21