Installation
Tunnel Placement
When placing a piece of equipment, tunnel depth will vary from site to site. Be sure to allow an
adequate operating envelope.
1) Position the assembled frame at 45” from the inside edge of the inside guide rail to the
outside edge of the driver side leg as shown beow.
2) While placing a level on the vertical surface of one of the legs, place shims under the base
plate as needed to make the assembly level in both directions. Repeat this leveling process
on the other side.
Note: Shims not supplied by Belanger, Inc.
3) Once the frame is positioned correctly and level in all directions, lag it to the floor using the
supplied lag bolts.
72”
operating
envelope
45”
DIRECTION
of
TRAVEL
45" dimension is taken from the outer equipment leg to the driver side edge of the inside guide rail
Dotted lines show proper operating envelope