Page 125 - Saber® Installation & Startup
P. 125
INSTALLATION & STARTUP
Chapter 7 Solution Delivery Module (SDM) / Pumping Station
Installing the XR Triple Foam Pods
Equipment Room Items to Connect
The SDM can be mounted on the wall or on the side of the Pumping Station. The Triple Foam Distribution Manifold may need to be
rotated to allow space for the port next to it.
Once the Triple Foma Maniold is secured in place, it is time to run the field supplied 1/2’’ poly flow tubing for the pneumatic run and
the 3/8” poly flow tubing for the chemical/water line from the equipment room through the Boom tie wraps and onto the machine. Be
sure to loop the lines enough to allow proper rotation of the Boom and a sufficient bend radius on the lines. Refer to the diagram
below to identify the connection locations.
Optional Triple Foam 2 Optional Triple Foam 3 Chemical / Water to Pods
Chemical / Water to Pods
Optional Triple Foam Air
Carriage Manifold Optional Triple Foam from valve on the Air Panel
Optional Triple Foam 1
Chemical / Water to Pods Optional Triple Foam 1 Chemical / Water from SDM
Optional Triple Foam 2
Chemical / Water from SDM
Optional Triple Foam 3
Chemical / Water from SDM
Pneumatic (Air) Panel: Back
Room Triple Foam
Manifold: SDM
Triple Foam Manifold: Carriage
The completion of installing the XR triple foam will be covered in the initial startup procedures later on in this manual.
1MANUL290 Belanger, Inc. * PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681 7-1