Page 140 - Saber® Installation & Startup
P. 140
INSTALLATION & STARTUP
Chapter 8 Wall Manifold / Optional Water Heater
Optional Water Heater Connections
Protective Cover
1) Wrap the insulation around the Super Heater and trim around the Uni-Strut mounts. Also cut a hole for the inlet hose barb.
Insulation
Cut hole in insulation to allow fitting to
come through
2) Position the aluminum cover over the Super Heater and clamp it into place. Since it is somewhat flexible, strech it out and
place it over the insulation making sure to line up the fitting with the holes.
Be sure to install a water hose for drainage. Failure to do so could lead to serious
injury due to 160° °°
° water discharging from the hot water safety relief valve.
Electrical Enclosure
Over-Temp Thermocouple
(Backside of 12kW Heating Element,
does not slide out)
Thermostat with Electronic ON/OFF
Control and Digital Display Over-Temp Module
As viewed, RED should be
one terminal above BLUE for
the Thermocouple wires on
Digital Display both Theremostat and the
Over-Temp Module
1 Amp-250V Fuse Terminal Strip
8-6 Belanger, Inc. * PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681 1MANUL290