FULL SIDE WASHER Signature ® Series
Installation
Positioning the Stands (Legs)
Note: The Legs will have to be leveled later during the installation, so do not pound any lag
bolts down all the way into the floor. Shims may also be required in the leveling process
although they are not supplied.
3) After making sure the stands are square to the conveyor, drill a 5/8” hole and place one 5/8”
lag bolt into place as shown below. Drill the other three holes.
Passenger Side Leg shown
Vehicle
Travel
Lag Bolts (typical)
Metal shim to assist in
leveling process (typical).
Use as necessary
The above image shows the use of four of the six holes in the base-plate. It may be necessary at your site to use
the two additional holes to properly level the unit. If that is the case, you will need to supply the additional lag bolts.
4) Place a small piece of steel or aluminum plate (shim) to assist in leveling. Shims are field
supplied.
5) Level both legs North, South, East and West
6) Now that the Stands are level, pound the lags all the way down.
7) Tighten the lag bolts.
Note: The legs will need to be leveled again after the Arms, Head Assemblies and Wash
Materials are installed.