Page 16 - Foam-X® Spray Arch
P. 16

®
            FOAM-X  SPRAY ARCH






            Installation



            Utilities
                   1)  Locate the supplied valve assemblies as shown below. There should be 4 of them.




                   2)  Apply Teflon tape to the threads and screw them into the holes on the junction boxes as
                       shown below. Be sure they are angled at about 45° towards the exit of the tunnel.













                   3)  Locate the 2 supplied sections of airline. One black and one natural colored. Also locate
                       the 2 supplied Tee’s and installed them as shown below.


























                   4)  Feed the appropriate airlines to the 2 Tee’s located atop the frame as shown below.

















             14             Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681          1MANUL215
   11   12   13   14   15   16   17   18   19   20   21