Page 14 - Pivoting Wheel Stinger™ Mix and Match
P. 14
PIVOTING WHEEL STINGER Mix and Match
Installation
Cylinder and Oil Reservoir Installation
1) Locate the reservoir/cylinder assembly and secure the reservoirs into place
using the supplied 1/4-20 x 1” fasteners and their appropriate lock washers as
shown below. Notice that the reservoir with the flow-control valve goes on the
top.
Valve
Control
Flow
Reservoir/Cylinder Assembly
Flow-Control Valve
2) Locate the hydraulic cylinder and secure it to the gusset using the supplied 3/4 x 1” shoulder bolt as shown
below. This is the shorter of 2 supplied shoulder bolts.
3) Attach the opposite end of the cylinder to the pivot control plate with the longer shoulder bolt 3/4” x 1-1/2”
through the cylinders rod end bearing through the locking bushing to the pivot control plate as shown below.
Note: The cylinder rod end is to be mounted on the exit side of the Pivoting Wheel Stinger
structure for optimal performance.
Bushing
1-1/2” Shoulder Bolt
1” Shoulder Bolt
Note: Hydraulic hose is run around the entrance side of the leg.
12 Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (810) 349-7010 * Fax (810) 380-9681 1MANUL586