Page 66 - Revit Architecture Basics
P. 66
DATE ELEMENTS
Creation of Levels
In order to create Levels, either a section or
elevation a view must be active.
Architecture ► Datum ► Level
Level Labels can automatically be made on line,
when they are drawn. Subsequently if a Level is
selected a locked padlock and a dashed line is
displayed at the same time. See point 1.
The lock icon indicates that the Levels are
"Aligned" or "locked on line", and that all Levels
will move the same, if one of the Level lines
is lengthened or shortened.
Paragraph 2 specifies that it is possible to
determine whether the Level labels (the main
symbol) should be displayed or not. This feature
is possible at both ends.
If a Level line has only to be extended or
shortened, click on the padlock to unlock it.
When forming Levels, you can choose on the Option Bar; Level should create a Plan View.
Option Bar
Level properties (Instance)
Elevation: Elevation on the specified level.
Story Above: Default is equal to the next Level specified as Building Story. Also used regarding
the breakdown of the walls and columns by IFC export.
Computation Height: Used in relation with volume calculations of space.
Name: Name of the current Level.
Structural: Specifies how the current Level is used in the context of constructions.
Building Story: Defines if the current Level is a floor Level or a Reference Level. Also used in
connection with "Story Above" at underlying Levels. Using View Range (Primary Range-Top),
only the Levels with Building Story will be enabled.
Design Option: Specifies which Design Option Level bar appears.
Scope Box: Indicates a possible applied Scope Box.
66 NTI