Milestone List
e table below outlines the major milestones that
were set out for the Nyayo village project.
Actual Date Of
Milestone Remarks
Completion
A Sample room/ Washroom
Construction of a sample room and a sample washroom and Jan, 2017 was done and approved
KYEB
before executing the rest of
approval from LOC/ IAAF
the work
Removal of existing fl oor tiles/ Pvc tiles
Completion of Nyayo Hostels 1 to 6 (Including Mechanical
June, 2017
and electrical works, Installation of solar water heating
system, Firefi ghting system, waterproofi ng, ICT network)
Completion of Nyayo Annex Flats (Anti-doping and Health
June, 2017
Unit)
Complete of Common Room 1 (Entertainment area) and
Common Room 2 (Athletes Massage area Board rooms and
Communication Centre)
Complete of Nyayo Kitchen including equipping and June, 2017
July, 2017
extension of ablution block.
KENYA YEARBO0K
Completion of a Police post
July, 2017
Refurbishment of the accreditation centre
EDITORIAL BOARD
External works (including landscaping, storm water
June, 2017
drainage, perimeter wall, walkways, ICT fi bre optic cabling)
June, 2017
Street Lighting and Roads accessing the Nyayo Village
Construction of a footbridge across the Railway line nil Works at 75%
Civil works complete
Supply and installation of all Tartan track including nil awaiting installation of the
associated civil works. tartan. Overall completion
– 85%