IAAF W ORLD U18 REPORT









                       MINISTRY OF TRANSPORT, INFRASTRUCTURE,
                       HOUSING & URBAN DEVELOPMENT




                       State Department of Public Works

                       Project Statuts Report For International Association Of Athletics Federations  IAAF  World
                       Under 18 Championships,  Nairobi 2017

                       Projects Status Report As At 12th January 2018
                   KYEB

                                           Local Organizing Committee, International Association of Athletics Federations
                       i) Client:
                                           (IAAF) World Under 18 Championship Nairobi 2017

                       ii)   Project Manager:  Works Secretary,Ministry of Transport, Infrastructure, Housing & Urban Development


                       1.   MOI INTERNATIONAL SPORTS CENTRE BUILDERS WORKS
                           WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141A

                           Main Contractor:

                                                           M/ S Ocean Bays Investment & General Supplies


                                                           P O Box 43059-00100


                                                           Nairobi

                                                           M/S Prowatt Enterprises Ltd
                           Nominated Contractor:
                      KENYA  YEARBO0K

                                                           P O Box 873-00600



                                                           Nairobi
                           A) Contract Data
                       EDITORIAL BOARD
                                  Contract Sum
                             i)
                                                                  Kshs. 101,896,093.6
                                                           -

                             ii)
                                  Commencement Date
                             iii)   Completion Date        -      6th February 2017
                                                           -             7th June 2017
                             iv)   % Work done             -      100%
                             v)    Amount certifi ed        -      Kshs 101,896,093.6
                             vi)   % of Amount Certifi ed   -      100%
                             vii)   Time Elapsed                  -   16 weeks
                             viii)   % of period lapsed     -     100%
                           B)   Scope of Works
                               i)   Construction of New Photo Finish Structure.
                               ii)   Tiling of Corridors and External Relaxing Areas (in Eurocon tiles)
                               iii)   Gypsum Ceiling Works in Offi  ces and Entry Porches
                               iv)   Concreting the fl oor areas below the terraces
                               v)   Paintworks and General Repairs
                               vi)   Creation of new ablution facilities for Media Centre (extra works)




                                                    ACTIVITIES AND OCCURENCES DURING WORLD U18 CHAMPIONSHIPS  | 237