vii) Media Tribune – Construction of podium and roof structure
viii) Rehabilitation of Changing Rooms
ix) Electrical Works
C) Status of the Works
General status is 100% complete as broken down below:
i) Photo Finish Structure 100% Complete.
ii) Tiling of Corridors 100% Complete
KYEB
iii) Gypsum Ceiling Works
100% complete
iv) Concrete Slab below Terraces
100% Complete.
and Plastering of Walls
v) Paint Works
100% Complete
100% complete
vi) Ablution Facilities
vii) Media Tribune Podiums
and Roof Structure
100% complete
100% complete
viii) Changing Rooms
ix) Extra Works – Creation of
100% complete
new MS Staircase
x) Electrical Works
100% complete
WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141B
2. MOI INTERNATIONAL SPORTS CENTRE BUILDERS WORKS
KENYA YEARBO0K
Main Contractor:
M/ S Funan Construction Limited
P O Box 43059-00100
Nairobi
EDITORIAL BOARD
M/S Glama Electrical & Mechanical Co. Ltd
Nominated Contractor:
P O Box 14615-00800
Nairobi
A) Contract Data
i) Contract Sum - KSh. 83,076,416.00
ii) Contract Period - 16 weeks
iii) Commencement Date - 6th February 2017
iv) Completion Date - 7th June 2017
v) % Work done - 100%
vi) Amount certifi ed - Kshs 83,076,416.00
vii) % of Amount Certifi ed - 100%
viii) Time Elapsed - 16 weeks
ix) % of period lapsed - 100%