                             Water reticulation

                              i)   Repair works on existing pipe work reticulation
                              ii)   Replacement and reinstatement of pumpsets
                             Water irrigation system


                              i)   Trenching, pipe laying and connections
                              ii)   Testing, backfi lling and compaction
                              iii)  Irrigation points and chamber construction

                   KYEB
                               C) Status of the Works

                              Overall status is 100% complete as broken down below:


                                                                                 100%

                              i)   Foundation Works and pump house

                              ii)   Tank installation and pipe connections
                                                                                 100%

                              iii)   Pump set supply and installation

                                                                                 100%
                              iii)   Repair works on existing pipe work reticulation
                                                                                 100%
                                                                                 100%
                              iv)   Replacement of leaking sections and fi ttings
                                                                                 100%
                              v)   Replacement and reinstatement of pump sets

                                                                                 100%
                              vi)   Trenching, pipe laying and connections
                              vii)  Testing, backfi lling and compaction

                                                                                 100%
                                                                                 100%
                              viii)  Irrigation points and chamber construction
                      KENYA  YEARBO0K
                       5.   MOI INTERNATIONAL SPORTS CENTRE, KASARANI – WARM-UP FIELDS – CIVIL WORKS
                           WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141J

                                                    M/S Resjos Enterprises Limited

                           Main Contractor:
                       EDITORIAL BOARD
                                                    P. O. Box 28689-00100




                                                    NAIROBI
                           A)  Contract Data
                             i)   Commencement Date        -      2nd  February 2017
                             ii)   Contract period         -      16 weeks
                             iii)   Completion date        -      2nd  June 2017
                             iv)   Revised Completion Date   -    N/A
                             v)   Contract sum             -      Kshs. 118,286354.80
                             vi)   Revised Tender sum      -      N/A
                             vii)  Amount Certifi ed to date   -   Kshs. 118,286354.80
                             viii) % Funds Certifi ed to date   -   100%
                             ix)   Contract Period         -      16 weeks
                             x)   Elapsed contract Period   -     16 weeks
                             xi)   % Work done             -       100%
                             xii)   Contract period elapsed   -   100%