IAAF W ORLD U18 REPORT









                       7.   MOI INTERNATIONAL SPORTS CENTRE –
                           ELECTRICAL INSTALLATIONS- WARM UP AREA AND OTHER EXTERNAL WORKS
                           WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141G

                           Main Contractor:               M/ S Muga Electrical contractors Limited
                                                    P.O Box 13328-00200
                                                    Nairobi

                           A) Contract Data

                              i)    Contract Sum        -   -     KSh. 58,252,621.00
                   KYEB
                                  Contract Period
                              ii)
                                                           -
                                                                  16 weeks
                              iii)   Commencement Date
                                                           -
                                                                  6th February 2017
                                                           7th June 2017
                              iv)   Completion Date
                                                           -

                                  % Work done
                              v)
                                                                  100%
                                                           Kshs 58,252,621.00
                              vi)   Amount certifi ed
                                                    -
                              vii)   % of Amount Certifi ed
                                                                  100%
                                                           -

                              viii)   Time Elapsed
                                                                  16 weeks
                                                           -
                              ix)   % of period lapsed  -
                                                           100%
                           B) Scope of Works
                              i)   Installation of Underground cables the warm up areas
                              ii)   Installation of Floodlights at the warm up areas
                              iii)   Changing and installation of lighting at Public Parking areas
                              iv)  Refurbishing, spray painting and rewiring of ceremonial lighting at circular drive
                      KENYA  YEARBO0K
                              v)   Replacement of Electrical fi ttings at the public toilets and ticketing boot
                           C) Status of the Works
                       EDITORIAL BOARD
                             General status is 100% complete as broken down below:
                               a)      e underground cables - 100% complete.
                               b)   Installation of the fl oodlights- 100% Complete
                               c)   Public Parking  – 100% complete
                               d)   Circular driveway- 100%
                               e)   Ticketing booths – 100% complete
                       8.  MOI INTERNATIONAL SPORTS CENTRE
                           –ELECTRICAL INSTALLATIONS- SITTING  TERRACES
                           WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141H


                           Main Contractor:              M/ S Muga Electrical contractors Limited
                                                    P.O Box 13328-00200











                                                   ACTIVITIES AND OCCURENCES DURING WORLD U18 CHAMPIONSHIPS  | 249
   244   245   246   247   248   249   250   251   252   253   254