Page 244 - World Under 18 Championships
P. 244

WORLD U18











                              Borehole Equipping

                              i)   Pump sizing, supply and installation
                              ii)   Trenching, pipe laying and connections
                              iii)  Cable supply, installation, connection and control equipment installation

                           C) Status of the Works

                              Overall status is 100% complete as broken down below:  100%

                  KYEB
                              i)   Borehole, drilling casing and gravel pack installation

                              ii)   Well development and test pumping

                                                                                 100%
                              iii)  Water testing, chemical analysis and well capping
                                                                                 100%


                              iv)  Pump sizing, supply and installation
                                                                                 100%
                              v)   Trenching, pipe laying and connections
                                                                                 100%

                              vi)  Cable supply, installation, connection and
                                 control equipment installation
                                                                                 100%
                       4.  MOI INTERNATIONAL SPORTS CENTRE, KASARANI - HIGH AND LOW LEVEL WATER
                           TANKS AND WATER RETICULATION INSTALLATION WORKS

                           WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141F
                           Main Contractor:
                                                    M/ S Walden East Africa Limited
                                                    P.O Box 8192-00200
                     KENYA  YEARBO0K
                                                    Nairobi
                           A)  Contract Data
                      EDITORIAL BOARD
                                                                  -


                                   Contract Sum
                              i)
                                                                          Kshs. 42,239,310.00
                              ii)

                                                                          6th February 2017
                                                                  -
                                   Commencement Date
                              iii)   Completion Date
                                                                  -             7th June 2017

                                iv)   % Work done                 -       100%
                                   High and low level water tanks
                                   Water reticulation             -       100%
                                   Water irrigation system        -       100%
                              v)    Amount certifi ed              -       Kshs 42,239,310.00
                              vi)   % of Amount Certifi ed         -       100%
                              vii)   Time Elapsed                    -    16 weeks
                              viii)   % of period lapsed          -        100%
                           B) Scope of Works
                              High and low level water tanks
                              i)   Foundation Works and pump house
                              ii)   Tank installation and pipe connections
                              iii)  Pump set supply and installation







               244 |  ACTIVITIES AND OCCURENCES DURING WORLD U18 CHAMPIONSHIPS
   239   240   241   242   243   244   245   246   247   248   249