J.6   Stone facework

                     l    Stone facework bonded to a backing of other material shall be given in square metres
                          stating the average thickness of the facowork.

                     2.   Stone facowork built against a backing of other material shall be given in square metres
                          stating the thickness of the facework. Wall-ties or anchors shall be given in the description
                          stating the type and spacing thereof and the method of securing to the backing.

                     3    Stone facework used as formwork shall be so described and given in square metres
                          stating the thickness. Temporary strutting shall be given in the description.

                     4.   Stone facowork built overhand shall be so described.

               J.7   Stone slabbing or cladding to walls

                     Stone slabbing or cladding to walls shall be given in accordance to Section S

               J.8   Rough cutting

                     1.    Rough notchings and rough sinkings for steel sections, concrete columns, concrete
                          beams and the like shall be deemed to be included with the items.

                     2.    Rough notchings and rough sinkings for gusset-plates' ends of joists and the like shall be
                          deemed to be included with the items.

               J.9   Fair cutting

                     Fair raking cutting and curved cutting on superficial items of stonework shall be given in metres
                     stating the thickness and radius. The extra stone required for curved cutting shall be deemed to
                     be included with the items.

               J.10   Rustications

                     Rustications shall be given in the description of the stonework on which they occur. Stops and
                     angles to rustifications shall be deemed to be included with the items.

               J.11   Grooves, rebates, margins, flutes, sinkings and angles

                     1.   Grooves, throats, rebates, margins, flutes, sinkings, chamfered angles, rounded angles
                          and the like labours on superficial items of stonework shall each be given separately in
                          metres stating the width or girth. Stops and mitres shall be deemed to be included.

                     2    Such labours on linear items of stonework shall be given in the description stating the
                          width or girth. Stops and mitres shall be deemed to be included.

                     3.   Such labours on enumerated items of stonework shall be given in the description stating
                          the width or girth. Stops and mitres shall be deemed to be included.

               J.12   Mouldings and enrichments

                     1.   Mouldings and enrichments on superficial items of stonework shall be given in metres
                          stating the girth and profile. Undercut mouldings and enrichments shall be so described.
                          Stops, mitres, returned ends and the like shall be deemed to be included.