Page 43 - Best Practices In Knowledge Transfer Programme(KTP) Phase 1
P. 43

IMPLEMENTATION OF
               PROJECT



      Objectives                         1.      To design and fabricate efficient steamed cooker for fish cracker process-
                                                 ing.
                                         2.      To design and fabricate efficient fish cracker cutting machine.
                                         3.      To improvise the work flow of production line to make it more productive.
      Methodology

       Activities Conducted               1.     Visit to fish factory in Perak to benchmark the process at collaborator’s
                                                 company.
                                          2.     Design for the equipment to be used in the process by Final Year student.
                                          3.     Collaboration between university and the company in fabrication of
                                                 equipment.
                                          4.     Seminar to company’s staff with regards to clean process and work
                                                 safety.
       Output                             1.     Design and fabrication of efficient steamed cooker for fish cracker (100%).
                                          2.     Design and fabrication of fish cracker cutting machine (100%).
                                          3.     Improvisation on the arrangement of production line to make it more
                                                 productive (100%).
                                          1.     Steamed cooker and fish cracker cutter fabricated facilitated to
       Industry                                  increase productivity of the factory.
                                          2.     Improvisation on arrangement of production line making the process
                                                 more efficient.
                                          3.     Work safety courses and HACCP certification conducted promoted
                                                 awareness on work safety and product produced.
       Public Higher Learning Institute   1.     Two (2) paper works produced for conferences - NCON PGR 2015 and
                                                 ICKT 2015.
                                          2.     Outcome of the project exhibited in Citrex 2014.
                                          3.     The project strengthened UMP’s image and credibility with the applicati-
                                                 on of problem-solving technology to nearby SME.
                                          4.     Learning through direct exposure to the students on industrial needs helps    33
                                                 the students to nurture their communication and project management
                                                 skills.
                                          5.     Technical skills obtained from fabrication work provide more confidence to
                                                 the students involved.
      Human Capital Development          1.     One (1) research assistant pursued study at postgraduate level through
                                                financing via this KTP grant.
                                         2.     Four (4) undergraduate students completed their thesis on the project.
                                         3.     Two (2) Diploma students completed their industrial training through
                                                collaboration with industry in this project.
                                         4.     Two (2) UMP’s alumni appointed as research assistant.
                                         5.     Three (3) technical staff facilitated in the fabrication of equipment
                                                designed.


                                                                                        PROBLEMS IDENTIFIED




     1.     The project need to be extended for six (6) months due to issue in quality of work and
            commitment of staff in fabricating the equipment.

     2.     Idea for improvisation proposed to the industry faced challenges for execution due to
            the mentality of staff which were difficult to accept new changes. Management of
            the SME also face difficulties to adopt strict approach as they need to manage their
            workforce which are difficult to be replaced.











     Best Practices in KTP
                                                                                  DR. MOHD ZAIDI BIN SIDEK
   38   39   40   41   42   43   44   45   46   47   48