➢  Painting two coats of interior acrylic latex enamel (Sherwin Williams ProClassic or similar) on all
               new construction interior millwork and doors.
            ➢  This scope of work anticipates the use of 1 ceiling color, 1 trim and door color, and up to 8 wall
               colors. Additional colors and/or extremely dark colors may increase the cost of materials and
               labor.

               HARWARE, GLASS, & MIRRORS
            ➢  Supply and install door hardware for all interior and exterior doors as per plans.
            ➢
            ➢  Supply and install bathroom accessory hardware for all bathrooms.
            ➢  In certain locations, the homeowner wishes to provide specialty/antique harware. Until these
               are provided, the cost to install could vary widely. Therefore, this scope of work includes an al-
               lowance for all specialty/antique installation.
               o  To avoid delays, homeowner must provide specialty harware prior to the harware trim-out
                   phase.
            ➢  Once all specialty hardware is on hand, an estimate for installation can be provided and ap-
               proved through BuilderTrend.
            ➢  Supply and install mirrors for all bathrooms.
            ➢  For the master bathroom, this scope of work includes one mirror for each vanity.
            ➢  For all other bathrooms, this scope of work includes one mirror.
            ➢  Supply and install shower glass door at master steam shower and all (4) upstairs tub/showers. A
               glass shower door / surround kit shall be installed at the garage shower.
            ➢  All hardware, glass, & mirror materials shall be handled as an allowance item and all final selec-
               tions shall be approved by the homeowner in BuilderTrend.

               APPLIANCES
            ➢  All kitchen & laundry appliances (new & salvaged) shall be handled as an allowance item (mate-
               rial & installation) and all final selections shall be approved by the homeowner in BuilderTrend.
            ➢  This scope of work does not include the repairs or replacement of salvaged appliances. Any/all
               damages caused by salvaged appliances (e.g. appliance leaks) shall be the responsibility of the
               homeowner.

               PLUMBING FIXTURES
            ➢  All plumbing fixtures (including material cost, taxes, delivery, etc.) shall be handled as an allow-
               ance item and all final selections shall be approved by the homeowner in BuilderTrend.

               ELECTRICAL FIXTURES
            ➢  All electrical fixtures (including material cost, taxes, delivery, etc.) shall be handled as an allow-
               ance item and all final selections shall be approved by the homeowner in BuilderTrend.

               LOW VOLTAGE
            ➢  No low voltage wiring is included in the scope of work.