Page 27 - Resumes.indd
P. 27

In addition, while this project did not require a New York City Site   West Wing Addition
        Safety Manager, Barr & Barr determined during preconstruction   Nearing the end of 2007 New York Hospital Queens requested
        that the challenges of this program warranted a full time Site Safety   that the Project Team prepare a plan to add two additional shell
        Manager.  Every worker was required to attend an employee orientation   fl oors to the West Wing Addition for future expansion.  Working
        related to that specifi c project before they were permitted to work   with the Team by March of 2008 a plan was in place to incorporate
        on site.  Barr & Barr also retained the services of an independent   the two additional fl oors.  Th  e critical path of this change was
        Safety Consultant.  As a team our Safety Manager and Consultant   the impact on the superstructure.  Th  e Project Team (Owner,
        would perform daily safety inspections of the site, workers, adjoining   Architect and Barr & Barr) developed a milestone schedule of
        properties, road and walkways servicing the site.  Barr & Barr   deliverables that were critical to the procurement and installation
        conducted weekly site safety meetings and at signifi cant points in   of the required steel, concrete, precast and curtainwall with the
        the project the Barr & Barr Team would coordinate meetings with   goal of accelerating these activities and minimizing the overall
        the subcontractors and workers to review changes in site logistics   impact to the project.
        and review methods of operations for signifi cant fi eld activities (i.e.:
        cranes, lift s, heavy equipment, scaff olds, hoists, etc.).  Barr & Barr’s logistic challenge was to implement a program that
                                                                 would allow the removal of roof, dunnage, stair and elevator steel
        Beginning with schematic budgets and concluding with an accepted   framing, prepare new concrete openings, and install new steel
        GMP, Barr & Barr produced eight (8) comprehensive budgets,   for the vertical expansion of these two new fl oors.  While all this
        including three (3) value engineering studies on the Parking Structure   is going on implement a phasing and sequence plan that would
        and fi ve (5) value engineering studies on the West Wing Addition.  allow precast and curtainwall construction to continue, as well
                                                                 as MEP interior roughing.
        Th  roughout this process Barr & Barr conducted regularly scheduled
        Master Planning Meetings with the Owner, Architect and their   Aft er vetting out all our options, including alternate means and
        consultants to review and advise on design status, costs, means,   methods, agreeing on a multi-phased occupancy plan (vs. the
        methods, materials, systems, logistics, permitting and schedule.  original single phase occupancy), the program implemented by
                                                                 the Project Team had less than a 8.5% impact ($10 million) to
        Th  is sharing of current project information kept the Project Team   the GMP and resulted in only three additional months to the
        informed with the latest project costs, schedules, phasing issues   project schedule.
        and potential impacts.


        The Parking Structure
        Initially the parking structure was intended to be a 3-story above
        ground facility.  During preconstruction the local community
        board expressed concerns and opposition to a parking structure
        in a predominately residential neighborhood.  New York Hospital
                                                                  PROJECT DETAILS
        Queens concerned about the impact of a prolonged DOB process and
        negative support from the community directed the Project Team to
        move forward on a three level fully underground parking facility.       •   A new 372 car garage was constructed
                                                                           on an adjoining site to replace the facility
        Th  is decision required a total redesign from the A/E Team and    that was removed to make way for the new
        required Barr & Barr to re-evaluate and develop a new logistics plan.    West Wing Addition.
        Th  e larger concern was how this decision would negatively aff ect
        the start of the West Wing Addition.  Originally these projects were
        scheduled to be sequential projects, Parking Structure followed by        •   Two shell fl oors were designed for an
        West Wing Addition.  Barr & Barr introduced a plan to New York     additional 80 Med/Surg beds in the future.
        Hospital Queens for the development of off site parking that would
        allow the existing parking structure to be vacated and demolished
        as originally scheduled and not impact the West Wing Addition        •   Multiple phases allowed the continued
        schedule.  Working with the Design Team a new program was          use of key areas of the hospital during
        established that would accommodate concurrent construction of      construction.
        the Parking Structure and new West Wing Addition.  Barr & Barr
        was able to incorporate this new plan within the established GMP.
                                                                         •   Rigorous infectious control program was
                                                                           established to ensure high standards were
                                                                           met by all.
   22   23   24   25   26   27   28   29   30   31   32