Implementation
        It was necessary for the project management staff  to reside on site
        throughout the duration of the project and required separation
        of project specifi c duties with multiple superintendents assigned
        to focus on critical building areas, scope and the required phases
        of work. Keith Lavery managed the Advance Work Package in
        advance of Phase I while Tim Senecal commenced site clearing,
        prep work & demolition for the Chemistry Additionas well as
        construction of the building site package for Phase I.  Jeff  Lloyd
        focused on the Phase I renovation projects in Hemenway Hall
        & Annex in dealing with the multiple sub phases of turnovers
        required and coordinated with Tim in tying in the various
        connectors, stairs & corridors to the new science building.
        During the summer phases an additional superintendent provided
        management of 2nd shift work in support of Jeff . Th e project
        management staff supported all day to day activities, issues,
        changes and additional work requested in order to maintain project
        schedules and meet deadlines.

        Upon successful completion of the major Phase I Project DCAMM    PROJECT DETAILS
        requested Barr & Barr to then move forward with Phase II which
        involved ADA upgrades throughout the existing buildings         •   Massachusetts Division of Capital Asset
        including but not limited to, door operators, ramp revisions, railing   Management & Maintenance (DCAMM)
                                                                          funded project.
        upgrades & bathroom upgrades. Furthermore,  renovations and
        improvements to Hemenway Hall & Annex continued which           •   A high standard of sustainability through
        included a completely new Nursing Suite & Simulation Lab Suite    the use of recycled and locally extracted
                                                                          and manufactured materials, low-VOC
        which again involved very close coordination with the school and   building products, low-mercury fl uorescent
        sub phasing. Jeff  Lloyd continued on as superintendent for Phase   lighting, storm water collection. LEED
        II along with our management team.                                Silver certifi cation.
                                                                        •   Th  e renovations upgraded the seismic,
        Completion                                                        structural, mechanical and electrical
        All sub phases were accomplished either ahead of schedule or      systems.
        on schedule and the school was able to set up and commence        •   Extensive hazardous materials abatement
        operations without missing a beat in any phase. Th  e entire project   was necessary for the existing Hemenway
        was completed on budget, exceeded the MBE/ WBE goal of 10.4%      Hall and Annex buildings.
        by an additional 5.8% and closed out fi nancially under budget        •   Early bid packages were required to
        within 3 months of the Certifi cate of Completion.                commence construction prior to the
                                                                          completion of the fi nal design documents.
                                                                          Th  ese early bid packages included
                                                                          selective demo, selective abatement, MEP
                                                                          infrastructure re-routing and extensive site
                                                                          work.
                                                                        •   Original 50% Design Development project
                                                                          estimate came in at 50% higher ($20
                                                                          million) than the original project budget.
                                                                          Th  rough intense value engineering and
                                                                          project re-design the team reached a GMP
                                                                          that was within 1% of the latest project
                                                                          estimate (70% Construction Documents).
                                                                        •   ADA upgrades throughout the existing
                                                                          buildings including but not limited to, door
                                                                          operators, ramp revisions, railing upgrades
                                                                          & bathroom upgrades.